Project

Huu Nghi - Chi Lang Highway

Role
General Contractor
Construction Package

Component 2: Investment and construction of the highway from Huu Nghi - Chi Lang border gate (Km1+800-Km44+749.67).

Bidding packages constructed by LICOGI 16 include:

XL09: KM 18+300-Km 20+000

XL10: Km20+000-Km22+400

XL11: Km22+400-Km24+000 (including bridge Km22+961)

XL12a: Km24+000-Km26+500

XL12b: Km26+500-Km29+000

XL14: Km29+000-Km32+000

XL15: Km32+000-Km33+500

XL27: Bridge Km21+060, Bridge Km 23+820

XL28: Km24+420 bridge, Km 25+460 bridge, Km26+00 . bridge

XL29: Bridge Km30+020

 The total value of construction is about 1,207 billion VND

Status

Under construction

Location

Lang So